FSP. Final Site Plan. Modification #1 to approved Development Order issued 12/12/2025. Project Manager: Samantha West This is a Final Site Plan application for a pallet board sawmill on a 51-acre parcel with a Prime Agriculture (A-1) zoning classification and Agricultural Resource (AR) future land use designation. A 9300 sq. ft. pole barn is proposed with Phase 1, and two additional pole barns (8400 sq. ft. each) and a modular office (1540 sq. ft.) with a parking lot are proposed with Phase 2. The parcel received...
The source's own wording of the request, unedited.
| Case number | 2026-F-FSP-0254 |
|---|---|
| Project name, as filed | Pallet Board Sawmill at SR-40 - Modification #1 |
| Address | 1375 E Sr 40, Deleon Springs 32130 |
| Case type | Final Site Plan |
| Product | Office |
| Site size | 50.3 acres |
| Approved | April 22, 2026 |
| Jurisdiction | Volusia County |
| April 22, 2026 | Approved |
Dates and wording are the source's own. Sources publish late and amend; the official record is the authority.
Site plan. A site plan is the detailed layout of a specific project on land that already has the zoning for it: the buildings, parking, drainage, access and landscaping. Most jurisdictions review it administratively or before a review committee, so it can move without a public hearing. Site plan approval is usually the last land use step before building permits. A permit, not the site plan, is what authorizes construction.
Every other tracked case on the same parcel, oldest first. A site's story usually runs across several cases.
| March 13, 2024 | Final Site Plan 2024-F-FSP-0248 approved |