DOS. Expansion of existing fuel farm at SWFIA, construct 3 new fuel storage tanks, new containment dikes, 2 new fuel truck offload positions, and associated modifcations to piping and stormwater drainage..
The source's own wording of the request, unedited.
| Case number | DOS2024-00162 |
|---|---|
| Project name, as filed | RSW Fuel Facility Improvements & Expansion |
| Address | 11000 Terminal Access Rd, Fort Myers |
| Case type | Site Development Order |
| Product | Industrial / logistics |
| Approved | August 27, 2025 |
| Jurisdiction | Lee County |
| August 27, 2025 | Approved |
Dates and wording are the source's own. Sources publish late and amend; the official record is the authority.
Site plan. A site plan is the detailed layout of a specific project on land that already has the zoning for it: the buildings, parking, drainage, access and landscaping. Most jurisdictions review it administratively or before a review committee, so it can move without a public hearing. Site plan approval is usually the last land use step before building permits. A permit, not the site plan, is what authorizes construction.
This source publishes no per-case link. Search the case number on the jurisdiction's own portal to pull the file.
Every other tracked case tied to this record, oldest first. A site's story usually runs across several cases.
| March 16, 1982 | Rezoning 82-02-08 (DCI) approved |
| November 14, 1983 | Special Exception 83-07-23 approved |
| April 16, 1984 | Special Exception 84-01-28 approved |
| May 19, 1986 | Special Exception 86-05-03 approved |
| 2000 | Site Development Order DOS2000-00051 approved |
| 2000 | Development of Regional Impact DRI2000-00000 approved |
| 2001 | Site Development Order DOS2001-00159 approved |
| 2001 | Site Development Order DOS2001-00218 approved |
| 2002 | Site Development Order DOS2002-00092 approved |
| 2002 | Site Development Order DOS2002-00185 approved |
| 2002 | Development of Regional Impact DRI2002-00007 approved |
| 2003 | Development of Regional Impact DRI2003-00004 approved |
| 2004 | Planned Development (DCI) DCI2004-00042 approved |
| 2004 | Special Exception SEZ2004-00041 approved |
| 2008 | Administrative Deviation / PD Amendment ADD2008-00162 approved |
| 2009 | Administrative Deviation / PD Amendment ADD2009-00065 approved |
| 2010 | Site Development Order DOS2010-00005 approved |
| 2012 | Administrative Deviation / PD Amendment ADD2012-00102 approved |
| 2012 | Site Development Order DOS2012-00033 approved |
| 2013 | Administrative Deviation / PD Amendment ADD2013-00184 approved |
| 2013 | Planned Development (DCI) DCI2013-00021 approved |
| 2015 | Site Development Order DOS2015-00067 approved |
| 2015 | Site Development Order DOS2015-00098 approved |
| 2015 | Site Development Order DOS2015-00100 approved |
| 2016 | Administrative Deviation / PD Amendment ADD2016-00026 approved |
| 2016 | Development of Regional Impact DRI2016-00014 approved |
| 2018 | Administrative Deviation / PD Amendment ADD2018-00015 approved |
| 2019 | Administrative Deviation / PD Amendment ADD2019-00027 approved |
| 2019 | Development project DOS2019-00139 approved |
| January 16, 2019 | Site Development Order 99-04-165.00D approved |