Case 2024-0412 · Rezoning · Office · City of Jacksonville
Building permit issued, construction authorized - New Building, est. $225,890 [B-25-332379.000] (4 more building permits followed). "New 3227 SQ FT metal building." Site work was authorized first, 2024-10-30.
The free brief covers new filings in this jurisdiction. It does not send a separate email for any one case.
ORD-Q Rezoning at 1249 St. Johns Bluff Rd N - (3.0± Acres) - IBP to PUD, to Permit a Pool Contractor’s Office With Parking of Related Heavy Equipment & Materials & Certain Other Industrial Business Park Allowed Uses, as Described in the Tempool PUD - Temple Holdings, LLC (R.E. # 161801-0030) (Dist. 2-Gay) (Fulton) (LUZ) (PD & PC Apv) 5/28/24 CO Introduced: LUZ 6/4/24 LUZ Read 2nd & Rerefer 6/11/24 CO Read 2nd & Rerefer 6/25/24 CO PH Only 7/16/24 LUZ PH Approve 7-0 7/23/24 CO Approve 18-0 LUZ PH - 7/16/24 Public...
The source's own wording of the request, unedited.
| Case number | 2024-0412 |
|---|---|
| Address | 1249 St Johns Bluff Rd N |
| Case type | Rezoning |
| Product | Office |
| Site size | 3 acres |
| Units stated in the filing | 1 |
| Requested zoning | IBP → PUD |
| Approved | July 23, 2024 |
| Jurisdiction | City of Jacksonville |
| May 28, 2024 | Introduced (City Council) |
| July 23, 2024 | Enacted (City Council · final) |
| January 14, 2026 | Building permit issued, construction authorized - New Building, est. $225,890 [B-25-332379.000] (4 more building permits followed). "New 3227 SQ FT metal building." Site work was authorized first, 2024-10-30. |
Dates and wording are the source's own. Sources publish late and amend; the official record is the authority.
Rezoning. A rezoning asks the local government to change the zoning district on a piece of land, which changes what can be built there and how much of it. It is decided by the elected board after a public hearing, usually with a recommendation from a planning board first, and takes effect by ordinance. Approval sets the entitlement. The owner still needs a site plan and building permits before construction starts, and each of those is its own step on the record.
Who decides what on this record:
See The Tracker · Watch the tool work on the free sample map
The free brief covers new filings in this jurisdiction. It does not send a separate email for any one case.