Case 2022-0713 · Rezoning · Multifamily · City of Jacksonville
Approved, no recent activity. Approved in November 2022.
The free brief covers new filings in this jurisdiction. It does not send a separate email for any one case.
The first line of the written brief, synthesised from this case's filed documents. The full brief is in the subscriber case file.
ORD-Q Rezoning at 8300 Merrill Rd, btwn Merrill Rd & I-295 Expwy E - (12.16± Acres) · PBF-2 & RMD-A to PUD, to Permit Residential & Associated Rec Uses, as Described in the Madison Palms Affordable Housing PUD · Lakeview Christian Fellowship, Inc., FKA Merrill Rd Baptist Church & Christian Ministry Center, Inc.; PUD Subject to Conditions (R.E. # 120735-0040) (Dist. 1-Morgan) (Abney) (LUZ) (PD & PC Amend/Apv) (Ex-Parte: CM DeFoor, Boylan, Salem, Becton, Priestly Jackson, Gaffney, Diamond, Howland, White, Morgan...
The source's own wording of the request, unedited.
| Case number | 2022-0713 |
|---|---|
| Address | 8300 Merrill Rd |
| Case type | Rezoning |
| Product | Multifamily |
| Site size | 12.16 acres |
| Units stated in the filing | 30 |
| Requested zoning | PBF-2 & RMD-A → PUD |
| Approved | November 22, 2022 |
| Jurisdiction | City of Jacksonville |
| September 27, 2022 | Introduced (City Council) |
| November 22, 2022 | Enacted (City Council · final) |
| September 29, 2023 | Building permit issued, construction authorized - New Building, est. $152,000 [B-23-652325.000] (8 more building permits followed). "The project consists of (8) 30 unit apartment buildings (all the same building type), 240 units total, with a stand alone clubhouse, mail kiosk, pavilion, tr..." Site work was authorized first, 2023-09-12. |
Dates and wording are the source's own. Sources publish late and amend; the official record is the authority.
Rezoning. A rezoning asks the local government to change the zoning district on a piece of land, which changes what can be built there and how much of it. It is decided by the elected board after a public hearing, usually with a recommendation from a planning board first, and takes effect by ordinance. Approval sets the entitlement. The owner still needs a site plan and building permits before construction starts, and each of those is its own step on the record.
Who decides what on this record: