Case FEDP-2026-0023 · Site plan review · Office · City of Winter Springs
215 Old Sanford Oviedo Rd, Winter Springs · aerial view
Notice of Commencement recorded · the owner has filed notice that work is starting on this parcel [inst 2026079990] (1 more notices on this parcel). A pre-construction notice under F.S. 713.13 (required for any job over $2,500); the recorded index does not say what the work is.
The free brief covers new filings in this jurisdiction. It does not send a separate email for any one case.
This work is for a new commercial building of approximately 5,000 GSF enclosed area and 580 GSF covered exterior area. The new building will be a pre-engineered metal building and will replace an existing double-wide construction trailer.
The source's own wording of the request, unedited.
| Case number | FEDP-2026-0023 |
|---|---|
| Project name, as filed | Garcia Civil Office |
| Address | 215 Old Sanford Oviedo Rd, Winter Springs |
| Case type | Site plan review |
| Product | Office |
| Site size | 1.75 acres |
| Jurisdiction | City of Winter Springs |
| January 6, 2026 | Application filed (Site Plan Review; city EnerGov record) |
| May 7, 2026 | Planning and Zoning Board hearing (Planning and Zoning Hearing, city workflow) |
| June 9, 2026 | City Commission hearing (Commission Hearing, city workflow) |
| August 11, 2026 | Notice of Commencement recorded · the owner has filed notice that work is starting on this parcel [inst 2026079990] (1 more notices on this parcel). A pre-construction notice under F.S. 713.13 (required for any job over $2,500); the recorded index does not say what the work is. |
Dates and wording are the source's own. Sources publish late and amend; the official record is the authority.
Site plan. A site plan is the detailed layout of a specific project on land that already has the zoning for it: the buildings, parking, drainage, access and landscaping. Most jurisdictions review it administratively or before a review committee, so it can move without a public hearing. Site plan approval is usually the last land use step before building permits. A permit, not the site plan, is what authorizes construction.