Case MPL2024-10022 · Master Plan · Multifamily · City of Orlando
5600 Major Blvd, Orlando · aerial view
Approved, and nothing new has appeared on the public record since. Quiet for about 26 months. A newer filing on this parcel has superseded this case.
| Case number | MPL2024-10022 |
|---|---|
| Project name, as filed | Condo Tower Master Plan |
| Address | 5600 Major Blvd, Orlando |
| Case type | Master Plan |
| Product | Multifamily |
| Site size | 1.74 acres |
| Approved | June 26, 2024 |
| Applicant of record | Nestor Diaz |
| Jurisdiction | City of Orlando |
| March 22, 2024 | Application filed |
| May 21, 2024 | MPB hearing (item 8) |
| June 26, 2024 | Approved (status: Closed) |
Dates and wording are the source's own. Sources publish late and amend; the official record is the authority.
Master plan. A master plan lays out the overall design of a larger project on land that already carries the zoning for it: buildings, access, parking, open space and phasing. It is reviewed against the rules that already apply rather than changing them. Approval of the master plan is a site-design sign off. Final site plans, plats where land is divided, and building permits follow.
Who decides what on this record:
Look this case up at Orlando planning-applications dataset →
Every other tracked case on the same parcel, oldest first. A site's story usually runs across several cases.
| March 24, 2025 | Master Plan MPL2025-10012 filed |
| July 16, 2025 | Master Plan MPL2025-10012 approved |
See the subscriptions · Watch the tool work on the free sample map · Subscriber? Open this case in the tracker